Organizing the recovery
Share
by Andrea   
Tuesday, 03 January 2012
The most requested items in this days are the power generators to fill up the communities' tanks (Photographer: Andrea)In this interview Sauro explains the plans and actions of the teams involved in the Thane cyclone recovery. The main priority is to supply power generators to fill up the communities' tanks scattered around Auroville. Generators has been rented and an order has been placed to buy 3 more of them. The Electrical Service is working from dawn to sunset preparing the installation of the main electrical lines which had been damage. There was no casualty in Auroville, all the guests are safe and the guest houses are open.

8 Mb



To come back to a normal power and electical supply it will take 10 to 15 days. (Photographer: Andrea)